Create Project Baseline

Summary

This article will help project manager's create a baseline for projects managed within the Enterprise Service Management system.

Body

Overview

A project plan is used to track the variance of a project over its duration against the original plan - or baseline. This article will provide project manager's with a guide for creating a baseline on a project managed within the Enterprise Service Management (ESM) system.

Important
A project may have at most ten (10) baselines associated with a project.

What materials do I need?

  • Internet connectivity
  • Web browser
  • TDWorkManagement access
  • Assigned as Project Manager, or Alternate Project Manager to the desired project

How do I use this technology?

  1. Login to UA ESM.
  2. Click Applications.
  3. Click Project.
  4. Click on the desired project name.
  5. On the project's Details page, click Actions.
  6. Click Add Baseline.
  7. In the Add Baseline dialog window, enter a succinct description in the Comments field about the baseline (e.g. Initial project baseline).
  8. Click Save.

Need additional help or have issues

For support, requests may be submitted anytime using the appropriate Enterprise Service Management form. Requests generate a Ticket which will be worked in order received and urgency by IT Employees with the knowledge and permissions to assist with the request.

For immediate assistance please review the Contact Us page for the appropriate support group.

Details

Details

Article ID: 2667
Created
Wed 12/10/25 12:00 PM
Modified
Wed 12/10/25 12:22 PM